The Port line to Uran, opened in three phases

Colour as time: a railway's track and stations painted by the phase each one opened in.

Read-only showcase
100%
The Port line to Uran, opened in three phases
In words

Everything on this map

The same content as the picture, as text: every part and what it says when you open it.

Phase I track: to Kharkopar

From Nerul and CBD Belapur to Kharkopar, with a halt at Seawoods. Commissioned on 1 November 2018 and opened on 11 November 2018.

Phase II track: Kharkopar to Uran

From Kharkopar to Uran, opened on 12 January 2024.

Nerul

A Harbour and Trans-Harbour line station. Port line trains start here, as well as at CBD Belapur.

Seawoods-Darave-Karave

A Harbour and Trans-Harbour line station, and a halt for Port line trains from Nerul.

CBD Belapur

A Harbour and Trans-Harbour line station. Port line trains start here, as well as at Nerul.

Targhar

Phase III, opened 15 December 2025. Station code TRGR. Built on track that had been running since the earlier phases.

Bamandongri

Phase I, opened November 2018. Station code BMDR.

Kharkopar

Phase I, opened November 2018. Station code KR/KARP.

Gavan

Phase III, opened 15 December 2025. Station code GAVN. Built on track that had been running since the earlier phases.

Shematikhar

Phase II, opened 12 January 2024. Station code SEMK.

Nhava Sheva

Phase II, opened 12 January 2024. Station code NESA.

Dronagiri

Phase II, opened 12 January 2024. Station code DRGI.

Uran

Phase II, opened 12 January 2024. Station code U/URAN. The end of the line.